Page 683 - Facilities Master Plan 2016
P. 683

Lodi Unified School District                                            Lodi Unified School District
          Plaza Robles High School                                                Turner Academy at Tokay Colony
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                           Project Cost Summary (2016$) - Plaza Robles High School             Project Cost Summary (2016$) - Turner Academy at Tokay Colony
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             18,470 sf  $                 5.40  01 Modernize & Reconfigure Aging Classrooms    $                       -  $                             -
            12i.2 Emergency Lighting             18,470 sf  $                 1.40  1b Replacement or repair of walls
            12j New public address/emergency communication                          1b.2 Repair walls                     3,840 sf  $               12.60
            systems                             18,470 sf  $                 7.60  1c Replacement or repair of windows
            12k Intrusion alarms                18,470 sf  $                 1.80 $              33,000  1c.1 Replace windows                3,840 sf  $               18.00
                                                                                   1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
          13 District Support Facilities                   $                       -  $                             -  1d.1 Replace doors & hardware                3,840 sf  $               13.50
            Not included in this Facilities Needs Assessment                       1e Replacement or repair of floors
                                                                                    1e.2 Repair floors                    3,840 sf  $               10.80
                                                                                   1f Replacement or repair of ceilings
          14 Outdoor Learning Environments & Quads         $                       -  $                             -  1f.2 Repair ceilings                3,840 sf  $                 8.10
            14b Learning Courts                                                    1g Patch & Paint Interior/Exterior
            14b.2 New Learning Court                5,400 sf  $               23.00  1g.1 Patch & paint interior                3,840 sf  $                 3.10
                                                                                    1g.2 Patch & paint exterior                3,840 sf  $                 4.50
                                                                                   1o Replace Existing Roofing                8,944 sf  $               20.93
           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
            15b PE Play Yard & Hardcourts
            15b.6 New Hardcourts                10,500 sf  $               11.00  02 Existing Building Systems & Toilets          $                       -  $                             -
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       12,666.67  2a HVAC system upgrades                3,840 sf  $               29.00
            15c Playfields
            15c.1 Repair Playfields             18,950 sf  $                 3.00  2b Lighting upgrades - new interior lighting & controls                3,840 sf  $               15.00
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
           16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -  outlets                3,840 sf  $                 9.00
            16a Flexible furniture (Per Classroom, Direct Cost)                        9 ea  $       15,000.00  2d Plumbing system upgrades                3,840 sf  $               11.00
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                   576 sf  $               83.00
           17 Technology Infrastructure                    $                       -  $                             -
            Not included in this Facilities Needs Assessment                       2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)                3,840 sf  $                 7.20
          Total Construction/Project Cost (2016$)          $              389,000  $517,000
                                                                                  03 Site Utilities                               $                       -  $                             -
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           423,403 sf  $                 0.16
          The following items are excluded from this budget:
           Utility hook-up fees & City connection fees.                            3b Updated sewer service lines           423,403 sf  $                 0.28
           Offsite work and traffic signals.                                       3c Updated water service lines           423,403 sf  $                 0.36
                                                                                                                    $
                                                                                   3d Updated electrical mains and distribution
                                                                                                             423,403 sf
                                                                                                                        0.45

           Land acquisition costs.                                                 3f Electrical Capacity Upgrades                        1 ls  $       57,500.00
           Hazardous material surveys, abatement, and disposal.
           Escalation (Costs are in 2016$ calculated to the end of the year).
                                                                                  04 Classrooms New Construction                  $                 11,000 $                      15,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        1 ea  $       11,000.00 $              11,000
                                                                                    4b.4 New Elementary Classroom Building (1-story)                3,168 sf  $             404.00
                                                                                    4b.10 Sitework & Site Improvements                3,168 sf  $               38.00
                                                                                  05 Maker Spaces & Science Labs                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  654
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District