Page 680 - Facilities Master Plan 2016
P. 680

Lodi Unified School District                                            Lodi Unified School District
          Liberty High School                                                     Liberty High School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                            Project Cost Summary (2016$) - Liberty High School                     Project Cost Summary (2016$) - Liberty High School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   12j New public address/emergency communication
          06 Electives                                     $                       -  $                             -  systems                 7,166 sf  $                 7.60 $              54,000
            6a MS/HS Electives                                                     12k Intrusion alarms                   7,166 sf  $                 1.80 $              13,000
            6a.5 Reconfigure MS/HS Electives Building                 1,236 sf  $             237.00  12n Elevator Repair and Cab Finishes                        1 ls  $       65,000.00 $              65,000
          07 Performing Arts Improvements                  $                       -  $                             -  13 District Support Facilities  $                       -  $                             -
            7a Music Lab                                                           Not included in this Facilities Needs Assessment
            8a.2 Modernize Music Lab                1,344 sf  $             135.00
                                                                                  14 Outdoor Learning Environments & Quads        $                       -  $                             -
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -  14b Learning Courts
            8a High School multipurpose rooms                                       14b.2 New Learning Court                   400 sf  $               27.60
            8a.4 New Multipurpose Room                1,120 sf  $             494.00
            8a.5 Sitework & Site Improvements                1,120 sf  $               38.00
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          09 Physical Education Improvements               $                       -  $                             -
            Not included in this Facilities Needs Assessment
                                                                                  16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
                                                                                   16a Flexible furniture (Per Classroom, Direct Cost)                        8 ea  $       15,000.00
          10 Administration & Staff Support                $                       -  $                             -
            10a Expanded, reorganized or relocated administration
            spaces                                                                17 Technology Infrastructure                    $                 32,000 $                      32,000
            10a.2 Modernize Administration                   440 sf  $             118.00   17c MDF and IDF data rooms with environmental control
            10a.3 Reconfigure Administration                   288 sf  $             235.00  (direct cost only)                         1 ea  $       32,000.00 $              32,000
            10a.4 New Administration                   368 sf  $             392.00
            10a.5 Sitework & Site Improvements                   368 sf  $               38.00
            10b Staff Collaboration/Work Rooms                                    Total Construction/Project Cost (2016$)         $              680,000  $893,000
            10b.2 Modernize Staff Collaboration/Work Rooms                     96 sf  $             118.00
            10b.3 Reconfigure Staff Collaboration/Work Rooms                   300 sf  $             235.00
                                                                                  The following items are excluded from this budget:
                                                                                  Utility hook-up fees & City connection fees.
          11 Library & Student Support Services            $                       -  $                             -  Offsite work and traffic signals.
            11b Middle School/High School Library/Innovation Lab                  Land acquisition costs.
            11b.4 Reconfigure Library/Innovation Lab                   368 sf  $             244.00  Hazardous material surveys, abatement, and disposal.
                                                                                  Escalation (Costs are in 2016$ calculated to the end of the year).
          12 Safety, Security & Campus Control             $              307,000 $                    408,000
            12a  Remaining asbestos removal                7,166 sf  $                 4.00 $              29,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.3 Entry Plaza                        875 sf  $               26.00
            12b.8 New Stair inc Railing                        2 ea  $       25,000.00 $              50,000
            12d Exterior lighting to ensure student safety                        1 ls  $       14,000.00 $              14,000
            12e Safety locks at classroom doors                     15 ea  $             449.00 $                 7,000
            12f Signage for emergency response and wayfinding                        1 ls  $       16,000.00 $              16,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                7,166 sf  $                 5.40 $              39,000
            12i.2 Emergency Lighting                7,166 sf  $                 1.40 $              10,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  651
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District