Page 14 - FreesStyler® Installation and Startup
P. 14
®
INSTALLATION AND STARTUP
Chapter 1 Introduction
Greetings
This Introduction Section is Intended to:
• Address the installation portion only.
• Help you to understand how the installation manual is organized.
• Encourage planning and organization.
• Safety Issues.
Owners Manual
This manual covers installation, Startup and Maintenance.
How the Manual is Organized
The installation manual starts off with a "punch list" of activities that must be performed during
the installation phase. The list is fairly comprehensive, and provides somewhat of an order in
which the tasks should be completed to minimize installation time.
One section of the installation manual is concerned with initial startup. Again, a checklist format
is provided to walk one through starting up the machine that has just been installed. The last
section includes Repair, Maintenance and Exploded Parts.
Planning and Organization
Planning and organization are the most important ingredients for a timely installation. At this
point much of the planning should have already been done. For example, your Belanger
Representative may have already visited the site. Measurements were taken, and quite possibly
drawings produced showing equipment locations.
The installation manual assumes that these items have been thoroughly looked at. If they
haven't, now is the time to do so. For your convenience, the "Getting Started" section reiterates
some of the critical points and primary equipment placement.
A Final Word on Safety
The job site can be a hectic place. Often deadlines control the pace. Please keep in mind Job
Site Safety at all times. Proper use of all safety gear (safety glasses, hard-hats, footwear,
shields, guards, etc.) is imperative. Be aware of electrical concerns (exposed conductors,
extension cords, proximity to water, power tool maintenance, etc.). Rigging (fork lift operation) is
another concern. Minimize slip, trip, and fall potentials consistently. In short, be aware of OSHA
considerations, in addition to rules and regulations put in place by your local authorities.
1-6 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL220