Page 170 - FreesStyler® Installation and Startup
P. 170

®
            INSTALLATION AND STARTUP


            Chapter 9 Optional “Add-On” Items


            Wheel Cleaning and CTA Options


               Wheel Stingers and Freestanding CTA - Utility Connections

               Applicators

                   3)  Run 1/2” and 1/4” poly-flow tubes from the tees of the Primary Applicator through the
                       cross over tube to the Secondary Applicator mount across the bay.















               Pressure Switch

                   1)  The Bell-Hose that was previously mounted across half the bay has to be connected to
                       the pressure switch inlet port. As vehicles run over the hose, it compresses. The resulting
                       displacement of air moves the diaphragm within the pressure switches enclosure.

                   2)  This switch should be mounted to the wall so that a 1/4” poly-flow tube can be connected
                       to the hose port. The switch can be mounted in a back room. The 1/4” poly-flow tube will
                       push up into the hose port on the electrical enclosure. The other end of the tube is to be
                       connected to the air fitting on the Bell-Hose Mount.
                   3)  Run field supplied S-O cord that will meet codes in your area from the enclosure on the
                       delivery  pumping  panel to the pressure switch enclosure. This will be wired normally
                       open.

               MixStir® Holding Tank and Delivery Pumping Panel

                   1)  Install a 3/4” ball valve to the main inlet water line will have to be run to the Hydro-Minder
                       inlet. A ball valve should be installed on this water line. There should be a hose between
                       the main supply lines to the inlet on the Hydro-Minder.
                   2)  Install a 1/2” ball valve to the field supplied main air line that will connect to the inlet of the
                       1/2” electric valve on the delivery pumping panel. This will supply compressed air to the
                       air pump and foam air regulator. This supply line should have a ball valve installed as
                       well.
                       See Nozzle Chart at the end of this chapter for more details.














            9-38        Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681       1MANUL220