Chapter 14 Foaming Sealer Wax and Foam-X Options
Foam-X
The Wall Manifold will have to be reconfigured using supplied components as shown below. Apply Teflon tape on all
fittings before installation.
Base (Existing) Pre-Soak
Manifold Assembly Fitting 2
Foaming Sealer Wax
or Foam-X Manifold
Assembly
Drying Agent and
Drying Agent and Wax Fitting
Wax Fitting
The Foam-X Option requires an additional chemical pump that will be wall mounted inside the equipment room. There
is also an additional water valve assembly that must be plumbed into the main water line with a field supplied tee as
shown below.
Below is an image of the additional Chemical pump mounted to the equipment room wall.