Page 51 - Saber® Installation & Startup
P. 51

INSTALLATION & STARTUP

                      Chapter 5 Electrical



                      General
                          Typically the electrical portion of the installation is the most substantial. Begin by referencing the
                          supplied  electrical  drawings,  and  reviewing  our  “Best  Practice  Methods”  within  this  chapter.
                          Understanding  the  electrical  requirements  for  the  Saber®  system,  in  addition  to  these  Best
                          Practice  Methods  will  not  only  assist  with  a  successful  installation  but  will  also  ensure  proper
                          future system performance.
                          A Saber® system will typically require between 30 and 40 man/hours to complete the electrical
                          installation. This assumes that the main supply lines to the building are in place.  If you have just
                          one electrician, assume that he will require between three and five days to complete the work,
                          depending upon hours worked per day. Please keep this in mind as you coordinate your project
                          resource schedule.


                      Electrical Standards Overview
                          This section will cover the required main electrical feeds needed for a standard installation.

                          Utilities
                          The following specifications are meant as a quick reference and guideline only. Your site may
                          vary  depending  on  your  setup,  configuration  and/or  local  code.  Contact  your  local  Belanger
                          Representative for questions.
                             Actual electrical requirements are dependent on state and local codes
                             Values listed below only valid for 208V systems. Contact factory if operating with voltage other
                             than 208/230V

                                      Item            Description      FLA    Service   Voltage   Phase
                                                                              AMPS
                                     Saber® MCC   Machine Control Center   80   100    208      3
                                      Saber® SCC   System Control Center   N/A   15    120      1
                                    Onboard Dryer   Dryer with 2, 10HP Motors   64   100   208   3
                                   Side Kick® Dryer   Dryer with 2, 10HP Motors   64   100   208   3
                                  Duo Dry™ System   Combined dryer system with    128   150   208   3
                                                     4, 10HP Motors

                                    Spot Free (RO)   Spot Free Water          (2) 20   208      1
                                                                     Contact your local Belanger Representative or
                                         Reclaim     Reclaim Pump       Belanger Technical Support Group @
                                                                               1-248-349-7010
                                    Water Softener   Kinetico Water Softener   N/A   N/A   N/A   N/A
                                      Compressor     Air Compressor
                                                     (not supplied)














                        1MANUL290        Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681   5-1
   46   47   48   49   50   51   52   53   54   55   56