Page 14 - Quad Wave Mitter Signature® Series
P. 14
QUAD WAVE MITTER Signature ® Series
Installation
Frame Assembly
The Head Assembly has the water manifolds secured into place at the factory. Determine which
side has the main water feed and be sure that side is oriented on the side of the utility room. See
image below.
1) Place the head assembly in its approximate tunnel location. Using a forklift, strap the head
assembly securely to the forks and raise above the height of the support legs.
Be sure to clamp or strap equipment securely to the forks of the fork lift before lifting
equipment. Do not stand under load while fork lift is in operation!
2) Locate the leg assemblies and the following fasteners.
1/2-13 x 6-1/2” bolts (8) 1/2” lock washers (8) 1/2” flat washers (16) 1/2” nuts (8)
3) Slide the legs into position and secure them to the head assembly as shown below.