             Installation

             Frame Assembly

                The Head Assembly has the water manifolds secured into place at the factory. Determine which
                side has the main water feed and be sure that side is oriented on the side of the utility room. See
                image below.












                1)  Place the head assembly in its approximate tunnel location. Using a forklift, strap the head
                    assembly securely to the forks and raise above the height of the support legs.




                        Be sure to clamp or strap equipment securely to the forks of the fork lift before lifting
                                 equipment. Do not stand under load while fork lift is in operation!

                2)  Locate the leg assemblies and the following fasteners.
                       1/2-13 x  6-1/2” bolts (8)  1/2” lock washers (8)   1/2” flat washers (16)   1/2” nuts (8)
                3)  Slide the legs into position and secure them to the head assembly as shown below.









































              10        Belanger, Inc. *PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681       1MANUL634