THE NEON STIK™


                       Installation


                       Assembly and Lagging to the Floor


                                                            CAUTION

                                 During installation care MUST be taken so not to damage the neon tubes.
                              1)  Position the Neon Stik™ assembly at the desired tunnel location.
                              2)  Remove the rear black plastic cover by squeezing the sides together.














                              3)  Level and lag into place. Replace the plastic cover.
                              4)  Remove the black plastic transformer cover from the top of the assembly.
                              5)  Supply 120VAC to The Neon Stik™ as shown below.

                                                 Transformer















                                            Hot
                                                           Common

                              Note:  A liquid tight 1/2” conduit, Seal-Tite™, or cord grip fitting MUST be used for electrical
                                     supply lines.
                              6)  Replace the plastic transformer cover.
















                        1MANUL519              Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681       9