Page 11 - The Neon Stik™
P. 11
THE NEON STIK™
Installation
Assembly and Lagging to the Floor
CAUTION
During installation care MUST be taken so not to damage the neon tubes.
1) Position the Neon Stik™ assembly at the desired tunnel location.
2) Remove the rear black plastic cover by squeezing the sides together.
3) Level and lag into place. Replace the plastic cover.
4) Remove the black plastic transformer cover from the top of the assembly.
5) Supply 120VAC to The Neon Stik™ as shown below.
Transformer
Hot
Common
Note: A liquid tight 1/2” conduit, Seal-Tite™, or cord grip fitting MUST be used for electrical
supply lines.
6) Replace the plastic transformer cover.
1MANUL519 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 9