Installation
Tunnel Placement
When placing a piece of equipment, tunnel depth will vary from site to site. Be sure to allow an adequate operating
envelope. The Wave Across can be installed facing either direction as there is no entrance or exit side.
®
1) Position the assembled unit in its permanent tunnel location.
2) While placing a level on the vertical surface of one of the legs, place shims under the base
plate as needed to make the assembly level in both directions. Repeat this leveling process
on the other leg.
Note: Shims not supplied by Belanger, Inc.
3) Once the assembly is positioned correctly and level, lag it to the floor using the supplied lag
bolts.
DIRECTION
of
TRAVEL
45” Center
Line
The 45” dimension is taken from the inside edge of the inside conveyor guide rail to the outside edge of the equipment leg.
Although the main water feed is shown on the driver side, it can be installed on either side.