             Installation


             Utility Connections for Side Wheels: Electric

                Water Feeds
                    1)  Unwrap the hose from around the Head Assembly and run it through the split grommets as shown
                       below and follow the shown path all the way to the junction box atop the leg assembly. Do not
                       tighten the clamps together until the conduit has been adjusted.
                    2)  From MCC Integra system panel, (see wiring  schematics)  drop the wiring 208-230VAC to the
                       electrical boxes on the top of the two QuickFire wrap legs you installed.


              Main power
                from drop                      3. Use wire-
                                                nuts to              1. From motor, down
                                               connect to             through conduit
                                               main power






                                            2. From one conduit, through
                                                           nd
                                           fittings and through 2  conduit







                    3)  Confirm that there is 20” of conduit at the area shown below and tighten all of the clamp fasteners.
                       Tighten all cord grips.














                                                                       20”


                    4)  When feeding wiring through cord grip in electrical boxes, use wire nuts and  electrical  tape  to
                       terminate wiring (see wiring schematics located in MCC panel).