Installation
Typical Pit Plan Use 2-1/2 x 2-1/2 x
1/4" angle steel
Use 4” x 1/2" dia. Re-rod
Weld
(typical) Use 3” x 1/2" dia. Re-rod
Angle iron with “Nelson Anchor”
(not supplied by Belanger, Inc.)
Cross section of both pits from entrance
front view
Place angle 4-1/2" 4-1/2"
and “Nelson depth Pit depth, 6” depth
Anchors” minimum minimum minimum
flush with
surface
(tpical)
6” cement slab
Slope pit towards drain
4” PVC drain to conveyor pit
(typical) (diameter of drain may vary or as required) 6 x 6 Wire mesh (10/10 GA)
Cross section of driver side Correlator pit and conveyor pit
side view
4” PVC drain to
conveyor pit
(diameter of drain may Driver side
vary or as required) Correlator pit
Conveyor surface 6” cement slab
Conveyor
Pit
6 x 6 Wire mesh (10/10 GA)
6” cement slab 12” concrete foundation wall
Note: The drain from the Correlator pit to the conveyor pit is to set between 1/16” to 1/8” below
the floor of the Correlator pit to prevent water settling.