Page 13 - Auxiliary Aluminum Arch
P. 13
AUXILIARY ALUMINUM ARCH
Installation
Tunnel Placement
When placing a piece of equipment, tunnel depth will vary from site to site. Be sure to allow an adequate
operating envelope
1) Position the Single Aluminum Arch in the exact tunnel location.
Overhead View
44”
Position Arch appropriately according to the site Conveyor style
44" dimensions are taken from the outer equipment leg to the driver side edge of the inside guide rail
2) Once positioned correctly and leveled, lag the arch to floor using a hammer drill with a 1/2" bit, and
the 1/2-13 x 3" quick lag bolts provided.
1MANUL032 Belanger , Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (810) 349-7010 * Fax (810) 380-9681 11