WIND POWER



                                                                                     The  southwest  region  of  the  County  of  Kings
                                                                                     presents  a  unique  opportunity  to  produce
                                                                                     renewable  wind  energy.  Our  lofty,  but  we  feel
                                                                                     attainable goal for this project is a wind farm that
                                                                                     produces in excess of 50MW. Though dependent on
                                                                                     turbine  size  and  wind  speed  through  the  rotor,
                                                                                     most wind turbines have a capacity of 2.5MW and
                                                                                     can produce about 6 million kWh in a year (enough

                                                                                     to supply 1,500 homes).

                                                                                     Before  we  get  too  far  ahead  of  ourselves,  this
                                                                                     project  will  require  significant  due  diligence.
                Goal:                                                                Specifically,  the  initial  phase  of  this  project  will
                Create  scalable  green  energy  production  in  the                 require a large amount of data collection to let us
                MOK for wholesale delivery to strategic partners.                    know  if  the  project  is  even  feasible.  This  would
                                                                                     include  determining  a  location  and  setting  up  a
                                                                                     meteorological tower to assess the amount of wind
                Why:                                                                 in the area.
                Economic  development  and  increased  financial
                sustainability  will  be  outcomes  of  this  project  as            Once testing is complete, Council will determine a
                well  as  reducing  reliance  on  non-renewable                      way  forward.  Financial  viability  for  large  wind
                electricity  sources  which  is  good  for  the                      probably requires an intake program which may or
                environment.                                                         may  not  be  enabled  by  the  Province  and  Nova
                                                                                     Scotia  Power.  The  Municipality  could  explore
                Anticipated Benefit:                                                 funding  renewable  wind  energy  as  a  new  revenue

                Production  of  clean  energy  and  the  introduction                source.  Another  option  could  be  to  seek
                of a new revenue source for the Municipality.                        development   partners.