Page 9 - Imagine Clearwater Proposal Digital
P. 9

Disney Village
LOCATION
Orange County, Florida
REFERENCE
Mr. Michael Carter
Blue Iron Foundations and Shoring, Inc. 467 Lake Howell Road, Suite 104 Maitland, FL 32751
Phone: 407.427.7051
Email: mcarter@blueironllc.com
DATE STARTED
Design 2013 - Construction 2014
DATE COMPLETED
Design 2014 - Construction 2015
PROJECT MANAGER
Timothy DeLand, PE
KEY STAFF
Je  Bergmann, PE Brian Rheault, PE
WGI was contracted by Disney Imagineering to assist in developing a pedestrian walkway and control structure for a newly created stormwater treatment area. Disney Village, located near Orlando, was renovated to include new shops and parking facilities. As part of the transfor- mation, a new stormwater treatment area was needed to provide a new settling lake for water quality and a control structure to limit the amount of water discharged. WGI was challenged with creating a structure that not only had the look and aesthetics of an old fashioned swing bridge, but that also could be constructed in a way to allow the adjacent properties to remain open during construction. Utilizing innovative design methodology and thinking, WGI sta  developed the walkway with a weir system utilizing structural steel sheeting and cast-in-place concrete. The weir system allowed water to  ow over the bisected lake/lagoon, providing the water storage and relief required to maintain the water quality. The sheet piles for the weir system were installed utilizing press-in technology which eliminated the vibration caused by conventional vibratory sheet installation. The press-in technology allowed adjacent properties to remain open during construction.
imagineclearwater DESIGN AND CONSTRUCTION CONSULTING SERVICES
2 firm’s experience/capability | page 8


































































































   7   8   9   10   11