Page 11 - Phelan Energy Green Ammonia Plant Egypt
P. 11
Executive Summary – Planned Project Growth
We agree with PEG that project size is an important factor for supply credibility. This Report outlines the Pilot Phase of 68,000 MT pa, which equated to a 250 MW solar plant installed capacity. The plant will grow to its planned capacity of 476,000 MT pa in three additional phases.
ITEM
Planned Project Growth
Pilot Phase
Phase 1
Phase 2
Phase 3
TOTAL
Total Annual Facility Capacity. MT pa
68,000
136,000
136,000
136,000
476 000
Solar Plant Installed Capacity
250MW
750MW
1250MW
1750MW
175MW
Capex (est) US$ Million
$420m
$840m
$840m
$840m
$2.9bn
Commercial Operation
Q4 2025
Q4 2027
Q4 2028
Q4 2028
© Phelan Energy Group 11