      Dutchess County Office                             100 Glens Street, Suite 3D, Glens Falls, NY, 12801  Captial District Office
      Phone: (845) 454‐3980                                        Phone: (518) 812‐0513  Fax: (518) 812‐2205  Phone: (518) 273‐0055
                                                            Web: www.chazencompanies.com
      Draft Opinion of Probable Cost for Town of Newcomb - Smart Growth Hamlet Plan              Date: November 2012
      Hudson River Bridge Enhancements
      Chazen Project No. 91145.00
                         Description                   QTY    Unit         Unit Price                Total Cost
      Hudson River Bridge Enhancements
      Unclassified Excavation                          200    CY            $6.00                    $1,200.00
      Asphalt Pavement (1.5" Top & 2.5" Binder)        600    SY            $20.00                   $12,000.00
      Subbase Type 2 (12")                             600    SY            $14.00                   $8,400.00
      Pavement Markings                                80     LF            $3.00                     $240.00
      Historic Pedestrian Lighting                      9     EA           $4,000.00                 $36,000.00
      Wiring & Conduit                                 550    LF            $20.00                   $11,000.00
      Trenching                                        550    LF            $5.00                    $2,750.00
      Entrance Gateway                                  1     EA           $5,000.00                 $5,000.00
      Informational Kiosk                               1     EA           $8,000.00                 $8,000.00
      Guide Rail                                       200    LF            $56.00                   $11,200.00
      Guide Rail End Assembly                           2     EA            $385.00                   $770.00
      Site Restoration                                  1     LS           $2,000.00                 $2,000.00
      Cantilevered Bridge Improvements                  1     LS             TBD                       TBD
                                                                              Total Route 28N        $98,560.00

                                                                    Construction Estimate Subtotal   $98,560.00
                                                                 Maintenance & Protection of Traffic  $0.00
                                                                              Mobilization (4%)      $3,942.40
                                                                       Project Contingency (20%)     $19,712.00
                                                                             Construction Total     $122,214.40
                                                    Legal, Technical, and Administravtive Allowance (15%)  $18,332.16
                                                                                      Total         $140,546.56