Page 59 - Town of Newcomb Smart Growth Hamlet Plan - 2013
P. 59

CHAZEN ENGINEERING, LAND SURVEYING & LANDSCAPE ARCHITECTURE CO., P.C.
      Dutchess County Office                              100 Glens Street, Suite 3D, Glens Falls, NY, 12801  Captial District Office
      Phone: (845) 454‐3980                                         Phone: (518) 812‐0513  Fax: (518) 812‐2205  Phone: (518) 273‐0055
                                                              Web: www.chazencompanies.com
      Draft Opinion of Probable Cost for Town of Newcomb - Smart Growth Hamlet Plan              Date: November 2012
      Bissell Loop Enhancements
      Chazen Project No. 91145.00
                           Description                  QTY    Unit         Unit Price               Total  Cost
      Bissell Loop Enhancements
      Pavement Excavation                               1,100   SY           $15.00                  $16,500.00
      Unclassified Excavation                            80     CY           $6.00                    $480.00
      Subbase Type 2 (12")                              1,000   SY           $14.00                  $14,000.00
      Asphalt Pavement (1.5" Top & 2.5" Binder)         1,000   SY           $20.00                  $20,000.00
      Pavement Markings                                  180    LF           $3.00                    $540.00
      Crosswalk                                          150    SF           $3.00                    $450.00
      Entance Gateway                                    1      EA          $5,000.00                $5,000.00
      Paver Patio                                        650    SF           $16.00                  $10,400.00
      Site Restoration                                   1      LS          $2,500.00                $2,500.00
                                                                               Total Route 28N       $69,870.00
                                                                     Construction Estimate Subtotal  $69,870.00
                                                                   Maintenance & Protection of Traffic  $2,000.00
                                                                               Mobilization (4%)     $2,794.80
                                                                         Project Contingency (20%)   $13,974.00
                                                                              Construction Total     $88,638.80
                                                      Legal, Technical, and Administravtive Allowance (15%)  $13,295.82
                                                                                       Total         $101,934.62
      1  This Opinion of Probable Cost  is intended to be used for order of magnitude pricing for budget purposes. Estimate is based on approximate dimensions measured from aerial
   54   55   56   57   58   59   60   61   62   63   64