      Draft Opinion of Probable Cost for Town of Newcomb - Smart Growth Hamlet Plan              Date: November 2012
      Blue Ridge Road Information Rest Area
      Chazen Project No. 91145.00
                           Description                  QTY    Unit         Unit Price               Total  Cost
      Blue Ridge Road Information Rest Area
      Unclassified Excavation                            250    CY           $6.00                   $1,500.00
      Subbase Type 2 (12")                               700    SY           $14.00                  $9,800.00
      Asphalt Pavement (1.5" Top & 2.5" Binder)          700    SY           $20.00                  $14,000.00
      Pavement Markings                                  250    LF           $3.00                    $750.00
      Entrance Pilars                                    1      EA          $5,000.00                $5,000.00
      Informational Kiosk                                1      LS          $8,000.00                $8,000.00
      Trees                                              1      EA           $600.00                  $600.00
      Site Restoration                                   1      LS          $2,000.00                $2,000.00
                                                                               Total Route 28N       $41,650.00
                                                                     Construction Estimate Subtotal  $41,650.00
                                                                   Maintenance & Protection of Traffic  $2,000.00
                                                                               Mobilization (4%)     $1,666.00
                                                                         Project Contingency (20%)   $8,330.00
                                                                              Construction Total     $53,646.00
                                                      Legal, Technical, and Administravtive Allowance (15%)  $8,046.90
                                                                                       Total         $61,692.90
      1  This Opinion of Probable Cost  is intended to be used for order of magnitude pricing for budget purposes. Estimate is based on approximate dimensions measured from aerial