Page 26 - 2016-R0
P. 26
Variation Order Contract Value Value of
Contract remaining Completion
Project Name After Variation
Value (SAR) Plus (SAR) Reduction works until end Percentage
(SAR) Order (SAR) of 2016 (SAR)
Infrastructures 5 Group 155,810,196 29,684,787 26,404,060 159,090,923 75,067,453 53%
Th
(Al-Khobar & Al Hassa)
South East Madinah Developing Project 4,581,337,513 4,581,337,513 100%
Infrastructures 3 Group
rd
(Skakka 1, Skakka 2, Turif, Quriyat, Arar, Rafha, Tabuk) 664,828,347 98,785,165 161,763,578 601,849,934 330,666,831 45%
Infrastructure Development of Jeddah Housing Project -
481,376,249 34,270,437 447,105,812 149,770,010 67%
RAYADA
Infrastructures of Hail University- 2 Package 440,000,000 20,153,644 34,812,206 425,341,438 119,592,093 72%
nd
nd
Jeddah / Mecca Highway -2 Package – 16 Km 300,00,000 11,929,000 288,071,000 206,954,982 28%
Completion of some agricultural roads in Jizan 124,000,000 6,200,000 117,800,000 68,044,548 42%
th
(14 Group)
Al- Dawadmi Housing Project 637,435,715 360,863,911 386,443,800 611,855,826 196,370,768 68%
Taiba-1 & 2. Housing Education for members at the Taiba
University 531,845,049 11,422,705 6,604,648 536,663,106 214,782,992 60%
Completion of Highway 4 -Matrifyah 199,367,856 11,853,539 211,221,395 21,169,741 90%
Road Join between King Abd-Allah Sport City & Jeddah 249,670,000 233,884,000 17,874,838 465,679,162 43,637,284 91%