Variation Order Contract Value
Contract Value of remaining Completion
Project Name After Variation Order works until end of 2016 Final invoice
Value (SAR) Plus (SAR) Reduction (SAR) (SAR) Percentage
(SAR)
Escada lift stations and systems in Jazan 11,116,471 11,116,471 2,775,860 75% 2,775,860
(14 stations)
Establishment of the main control and
control center in Jizan 6,180,000 6,180,000 4,450,000 27% 4,450,000
Dammam Sewage Treatment Plant 23,627,467 23,627,467 976,449 96% 976,449
Project (Second Phase)
Establishment of Arafat station 68,491,410 68,491,410 6,849,142 90% 6,849,142
Establishment of Al-Sharaa 2 74,390,000 74,390,000 7,456,301 90% 7,456,301
transformation station
Establishment of Zahra transformation
station 74,390,000 74,390,000 17,225,406 77% 17,225,406
Establishment of Al-Flah station 70,794,071 70,794,071 7,418,832 90% 7,418,832
Establishment of Al-Mansora station
70,794,071 70,794,071 14,466,918 80% 14,466,918
Establishment of Al-Faisalia station 70,794,071 70,794,071 14,473,273 80% 14,473,273
Total or Ongoing Projects 1,367,205,101 2,400,000 42,477,565 1,327,127,536 172,525,022 87% 172,525,022