Page 28 - 2016-R0
P. 28

Variation  Order         Contract Value    Value of remaining
               Project Name                         Contract                                  After Variation   works until end of   Completion    Final
                                                   Value (SAR)     Plus (SAR)   Reduction      Order (SAR)         2016 (SAR)      Percentage    invoice
                                                                                   (SAR)
     Completing some roads in Jazan Region (Group II)  84,99,911    8,499,991                  93,499,902          9,354,395          90%        9,354,395

        Construction of highways (3) for Jubail (2)  258,383,462                               258,383,462        17,793,896          93%       17,793,896

                 Maydeen Al Kharj 1                186,674,102      3,275,369                  189,949,471        12,404,836          93%       12,404,836


      Execution of secondary roads in Riyadh (Group I)  524,737,171  34,146,829                558,884,000        34,146,830          94%       34,146,830

      The first part of the first phase "civil works of the   3,871,734,504                   3,871,734,504                          100%          -----
           railway" for the project of the HHR

     Execution of sewerage networks in the Damad City   104,493,491              16,809,596    87,683,895          3,306,184          96%        3,306,184
                   in Jazan Region

       Water treatment Plant on wadi Damad dam in   82,813,972                    1,242,902    81,571,070         10,596,584          87%       10,596,584
                    Jazan Region
         Establishment Station in  Buraidah West   68,850,000                                  68,850,000          9,606,221          86%        6,885,000

              Establishment Mecca Station          72,165,135                                  72,165,135          9,577,512          87%        7,216,514
             Establishment Al-khafji Station        79,980,000                                  79,980,000        18,239,168          77%        7,998,000

     Establishment transformation Station in Thool City
                                                   76,354,460                                  76,354,460         18,475,787          76%        7,635,446

       Establishment transformation beach Station   80,445,000                                 80,445,000         19,012,769          76%        8,044,500
             Establishment Nemar Station            76,426,541                                 46,462,541         18,064,446          76%        7,642,654

                       Total                       5,568,057,749    45,922,189  18,052,498     5,595,927,440      180,578,629         97%       133,024,839