Princeton University, Offi  ce of Design & Construction

                                      Peretsman-Scully Hall & Princeton Neuroscience Institute


































          SIZE                     OWNER
          249,000 square feet      Princeton University, Offi  ce of
                                   Design & Construction
          CONTRACT TYPE
          Construction Manager-at-Risk  ARCHITECT
                                   Jose Rafael Moneo (Madrid,
                                   Spain)
                                   and Davis Brody Bond




                                                                       PROJECT DETAILS
         Th  e home for the Peretsman-Scully Hall and Princeton Neuroscience          •    Building Information Modeling (BIM)
         Institute and the Department of Psychology, this two-building complex   was utilized for clash detection as part of
         houses a state-of-the-art data center, research facilities, teaching classrooms,   the constructability review and mechanical
         faculty offi  ces, wet and dry laboratories,  a lecture hall, vivarium, and   coordination. Th  e BIM model also provided
         MRI’s and RF shielded rooms.                                        As-Builts for facility management and
                                                                             operations.
         A high standard of sustainability included natural lighting, automatic
         lighting controls, a stormwater reclamation system for non-potable use, a          •   Extensive design and performance testing
         high performance exterior façade featuring outer ribbed glass sunscreen   ensured the viability of the custom glazed
         and inner high-performance glass, an energy effi  cient HVAC system   double curtain wall system.
         including heat-recovery system and low fl ow plumbing fi xtures.          •   An underground tunnel connects the
                                                                            buildings to the Barr & Barr built Carl Icahn
                                                                            Laboratory located north of the project site.
                                                                            •   An extensive sitework utility enabling project
                                                                            was required in order to facilitate the new
                                                                            construction.
                                                                            •   We minimized disruptions to the University
                                                                            campus and surrounding neighborhood
                                                                            through in-depth preconstruction logistics
                                                                            planning.