Page 81 - 1.Table Of Contents.indd
P. 81
PROJECT DOCUMENTATION: $ -
As-Built/Extra Drawings 1 LS $ 10,000 $ 10,000 $ 10,000
Aerial Photography 1 LS $ 2,500 $ 2,500 $ 2,500
Progress Reports 18 MO $ 250 $ 4,500 $ 4,500
Record Retention 1 LS $ 12,000 $ 12,000 $ 12,000
$ -
$ -
SITE MAINTENANCE: $ -
Small Tools/Equipment 1 LS $ 21,500 $ 21,500 $ 21,500
Field Toilets 18 MO $ 600 $ 10,800 $ 10,800
Temp Tank 18 MO $ 350 $ 6,300 $ 6,300
Dumpster Fees 18 MO $ 1,500 $ 27,000 $ 27,000
Ice/ Ice Machine 18 MO $ 250 $ 4,500 $ 4,500
Storage Cleaning Supplies 18 MO $ 150 $ 2,700 $ 2,700
Jobsite Fuel 18 MO $ 350 $ 6,300 $ 6,300
Field Signage 1 LS $ 2,500 $ 2,500 $ 2,500
$ -
SITE SAFETY SUPPLIES: $ -
Fire Extinguishers 100 EA $ 75 $ 7,500 $ 7,500
Safety Equipment 1 LS $ 4,500 $ 4,500 $ 4,500
Opening Protection 1 LS $ 3,500 $ 3,500 $ 3,500
Temporary Rails 1 LS $ 4,500 $ 4,500 $ 4,500
GRAND TOTAL GENERAL CONDITIONS $ 236,800 $ 2,037,481 $ 2,274,281
*Units should be listed in hours or weeks, lump sum, each or allowance