PROJECT DOCUMENTATION:                                                    $           -
 As-Built/Extra Drawings  1 LS  $     10,000  $        10,000              $        10,000
 Aerial Photography  1 LS  $       2,500  $       2,500                    $         2,500
 Progress Reports  18 MO  $       250  $       4,500                       $         4,500
 Record Retention  1 LS  $     12,000  $        12,000                     $        12,000
                                                                           $           -
                                                                           $           -
 SITE MAINTENANCE:                                                         $           -
 Small Tools/Equipment  1 LS  $     21,500  $        21,500                $        21,500
 Field Toilets  18 MO  $       600  $        10,800                        $        10,800
 Temp Tank  18 MO  $       350  $       6,300                              $         6,300
 Dumpster Fees   18 MO  $      1,500  $        27,000                      $        27,000
 Ice/ Ice Machine  18 MO  $       250  $       4,500                       $         4,500
 Storage Cleaning Supplies  18 MO  $       150  $       2,700              $         2,700
 Jobsite Fuel  18 MO  $       350  $       6,300                           $         6,300
 Field Signage  1 LS  $       2,500  $       2,500                         $         2,500
                                                                           $           -
 SITE SAFETY SUPPLIES:                                                     $           -
 Fire Extinguishers  100 EA  $       75   $       7,500                    $         7,500
 Safety Equipment  1 LS  $       4,500  $       4,500                      $         4,500
 Opening Protection  1 LS  $       3,500  $       3,500                    $         3,500
 Temporary Rails  1 LS  $       4,500  $       4,500                       $         4,500



 GRAND TOTAL GENERAL CONDITIONS  $       236,800   $     2,037,481         $      2,274,281



 *Units should be listed in hours or weeks, lump sum, each or allowance