PROJECT DOCUMENTATION: $ -
As-Built/Extra Drawings LS $ 10,000 $ - $ -
Aerial Photography LS $ 2,500 $ - $ -
Progress Reports MO $ 250 $ - $ -
Record Retention LS $ 12,000 $ - $ -
$ -
$ -
SITE MAINTENANCE: $ -
Small Tools/Equipment LS $ 21,500 $ - $ -
Field Toilets MO $ 600 $ - $ -
Temp Tank MO $ 350 $ - $ -
Dumpster Fees MO $ 1,500 $ - $ -
Ice/ Ice Machine MO $ 250 $ - $ -
Storage Cleaning Supplies MO $ 150 $ - $ -
Jobsite Fuel MO $ 350 $ - $ -
Field Signage LS $ 2,500 $ - $ -
$ -
SITE SAFETY SUPPLIES: $ -
Fire Extinguishers EA $ 75 $ - $ -
Safety Equipment LS $ 4,500 $ - $ -
Opening Protection LS $ 3,500 $ - $ -
Temporary Rails LS $ 4,500 $ - $ -
GRAND TOTAL GENERAL CONDITIONS $ - $ 271,550 $ 271,550
*Units should be listed in hours or weeks, lump sum, each or allowance