Page 36 - ATA
P. 36

principal ta finalisa y e siguiente 5 companianan lo participa den e proceso di tender: Aecon
               Group  Inc.,  Ballast  Nedam  International  Projects  B.V.,  Bam  International  B.V.,  Bouygues
               Batiment International y Tav Tepe Akfe Construction & Operation Co. E contratista cu wordo
               selecta lo ta responsabel pa e construccion di e expansion di e terminal y tambe e cambionan y
               mehoracion di e caminda y parkinglot. E documento di Tender y tur pintura tecnico a wordo

               entrega dia 31 di Mei y e bishitanan na e sitio lo wordo plania den fin di Juni. Tur bid ta wordo
               spera             di            wordo             ricibi           den             September.
               “Nos  ta  ansioso  cu  e  siguiente  stap  di  e  proyecto  Gateway  2030.  E  participacion  di  e
               companianan  di  construccion  internacional  cu  hopi  experiencia  lo  brinda  e  conocimento  y

               experticio necesario pa di forma efectivo realisa nos programa di construccion y tambe brinda
               oportunidad y partnership cu subcontratistanan local pa traha hunto cu nan pa brinda tambe
               oportunidad di empleo local. E expansion di e terminal cu 34.000 m2, den un tempo estima di 4
               aña  di  construccion,  lo  brinda  e  upgrade  di  capacidad  y  servicio  necesario  pa  e  cantidad
               creciente di pasahero cu ta pasa door di nos aeropuerto tur dia. Nos ta hopi satisfecho cu e
               experiencia y experticio di e companianan di construccion cu a precualifica pa participa den e

               bid y nos ta confia cu e proceso lo culmina cu resultado positivo. Nos ta ansioso pa mira e
               construccion tuma lugar pa Aeropuerto di Aruba su Proyecto di infrastructura,” asina AAA su
               CEO                Sr.             James               Fazio              a              bisa.


               Aruba     Airport’s   Gateway     2030     project   stepping    into    the   next    phase:
               Five international construction companies to bid for the Gateway 2030 expansion project of the
               Main                                      Building                                    Contract

               ORANJESTAD  –  Aruba  Airport  Authority  N.V.  (AAA)  together  with  its  project  partners  have
               finalized the design and tender documents for the main terminal construction, and completed

               the  prequalification  for  the  contract  bids  for  the  main  terminal  construction.  The  preparation
               works and relocation and upgrading of the airport’s main utilities are well underway, and the
               next  phase  will  complete  the  remaining  planning  process  and  move  the  project  into  a  full-
               construction                                                                            stage.

               The results of the prequalification process for the Main Building construction contract has been
               completed and the following five companies will be participating in the tendering process; Aecon
               Group  Inc.,  Ballast  Nedam  International  Projects  B.V.,  Bam  International  B.V.,  Bouygues
               Batiment  International,  and  Tav  Tepe  Akfe  Construction  &  Operation  Co.  The  selected
               contractor  will  be  responsible  for  the  construction  of  the  terminal  expansion,  as  well  as  the
               roadway  and  parking  lot  changes  and  upgrades.  The  Tender  Documents  and  all  technical

               drawings have been delivered on May 31st, site visits are planned for mid to late June, and final
   31   32   33   34   35   36   37   38   39   40   41