Page 60 - SOP Final
P. 60
SOP FOR NBA, NAAC & NIRF
Objective: To elaborate the procedure for preparing the Guidelines of NBA, NAAC, NIRF
related work.
Responsibility:
Principal / Registrar
Dean
HoD
All Teaching Staff
All Non-Teaching Staff
Procedure: NBA
Target
Sl. Activities Responsibility
dates/days
15 days before the
Preparation of details required for
1. Faculty Incharge application
Prequalifier application
Submission
10 Days before
Internal Verification of Prequalifier
2. Principal, Dean & HODs the application
application
submission
Preparation of final Copy application
3. Faculty In charge 10th Day
and Uploading in the e-nba portal
Criterion Incharge meeting with
4. Principal regarding the preparation of Faculty In charge of 11th to 15th day
concerned department, HOD
SAR and files
5. Preparation of SAR and related files Faculty Incharge & HOD 16th to 60th day
6. Verification by Department HODs Faculty Incharge & HoD 61st to 65th day
Improvisation of SAR and Files from the Faculty Incharge, HoD &
7. 66th to 70th Day
feedback and comments of Dean Dean
Verification by Principal and Other Principal, Registrar & Other
8. 71st to 75the day
Department HODs Department HODs
Page 53 of 245