Page 62 - SOP Final
P. 62
Procedure: NAAC
Sl. Activities Responsibility Target dates/days
Criterion Incharge meeting with
1. Principal regarding the preparation Director IQAC 1st to 5th day
of SSR and files
Preparation of SSR and related Director IQAC,
2. 6th to 50th day
supporting documents Coordinator IQAC
3. Verification of Criteria Criteria In charge 51st to 55th day
Improvisation of SSR and Files from
4. the feedback and comments of Coordinator IQAC & 56th to 70th Day
Principal / Registrar Criterion In charge
Director IQAC,
Verification by Principal and
5. Coordinator IQAC & 71st to 75the day
Registrar
Criterion In charge
Improvisation of SAR and Files from
6. the feedback and comments of Coordinator IQAC & 76th to 80th day
Principal Criterion In charge
Director IQAC,
Final SSR verification by Principal,
7. Coordinator IQAC & 81st to 85th day
Registrar & Expert
Criterion In charge
Director IQAC &
8. Submission of SSR 86th to 90th day
Coordinator IQAC
Coordinator IQAC &
9. File updation 91st to 120th day
Criterion In charge
Principal &
10. Conducting Mock NAAC visit 121st 125th day
Registrar
Improvisation of SSR and Files from
11. the feedback and comments of Coordinator IQAC & 126th to 150th day
Criterion In charge
Expert Members
Fine Tuning of Files and Coordinator IQAC &
12. Till Committee Visit
Documents Criterion In charge