E001 RevC, E300 RevA.
Hydraulic Services;
H001 Rev2, H051 Rev2, H053 Rev2, H101 Rev3, H052 Rev2, H112 Rev4, H151 Rev3, H201 Rev1,
H202 Rev1, H212 Rev1, H102 Rev4.
Costing Breakdown Summary
Description $ Cost (Excluding GST)
Site Establishment and Waste Removal $16,650.00
BWIC’s $85,300.00
Height Access $125,000.00
Demolition $132,200.00
Partitions, Ceilings and Doors $409,280.00
Joinery inc Smart Boards $588,103.00
Painting $70,750.00
Floor Finishes $148,730.00
Tiling $19,600.00
Electrical Services $438,333.00
Communication Services $47,100.00
Mechanical Services $446,982.00
Fire Services $19,376.00
Hydraulic Services $324,024.00
Glazing Film $1,824.00
Window Treatments $58,060.00
Compactus $13,580.00
Operable Walls $69,110.00
Excavation Works and Landscaping $67,750.00
Concrete Cutting and New Concrete Works $70,700.00
Steel Works $182,163.00
Provisional Sum - Asbestos Removal $80,000.00
Provisional Sum – Hydraulic Pit $8,000.00
Provisional Sum – Stage Extension $10,000.00
Provisional Sum – Irrigation System $5,000.00
Provisional Sum – Access system and handrails for Mechanical Platform $10,000.00
Provisional Sum- Fire rating steel members $30,000.00
Provisional Sum -Signage for Auditorium Awning $4,000.00
Provisional Sum - Builders works acossicted with nominated items (see
clarifications) $70,000.00
Jands $218,537.00
7 | P a g e