Page 8 - Boss Submission Merici College
P. 8

DynaFlow                                                                             $79,962.00
                Easy Living Stair Lift                                                               $48,000.00
                AV Lifts Australia/ Dumbwaiters                                                      $22,319.00

                Overheads, Preliminaries and Margin                                                 $310,395.00
                TOTAL EX GST                                                                      $4,230,828.00
                GST                                                                                $423,082.80
                TOTAL INC GST                                                                     $4,653,910.80

               BOSS TENDER CLARIFICATIONS & PROJECT RISK


               Boss Project Group Tender Clarifications

                       We have made no allowance for the cost of a building permit, or any other authority or statutory
                       fees.
                       Unless specified, we have made no allowance for the separation of power or the installation of
                       new metering.
                       We have made no allowance for temporary power or water and have assumed that will be
                       provided free of charge.
                       We have allowed for toilet facilities as part of our isolated site compound.
                       We have allowed for temporary fencing and hoardings as required to the three stages of work
                       areas.
                       Our tender has been prepared on assumption that specified items by nominated suppliers can be
                       procured within the project time frame.
                       We have made no allowance for private certification or architectural drawings
                       We have allowed for all trade certification.
                       We have allowed for trade clean and rubbish removal
                       We have allowed for Site Supervision and WHSQE Compliance in our quotation
                       We have for a standard glazing band for compliance. We have not allowed FM01 Glazing Film or
                       any glazing film with Merici Logo specified as graphic quality, size and design will have to be
                       confirmed.
                       We have allowed for scaffolding within the auditorium.
                       We have allowed for safety signage and other compliance requirements on site.
                       We have allowed for a full time site manager, project manager and contract management.
                       We have not allowed for cutting or reinstatement of concrete slabs over 150mm
                       We have not allowed for any core holing over 150mm
                       We have allowed for a curtain to be provided by JANDS to conceal the lift structure when fully
                       extended into the auditorium.


               Boss Project Group Identified Risk *

               Identified Risk forms part of the Tender Clarifications
                       No AV Design or specification has been provided - We have not allowed for any AV
                       Services, AV Equipment or associated works including;
                       Cabling from floor boxes to AV Control Room or any other power or data cabling associated
                       with AV Services, Supply and Installation of any AV Racks, Supply and Installation of
                       Motorised Projectors, Supply and Installation of TV’s etc.






                                                                                                   8 | P a g e