No Security Design or Documentation has been provided - We have not allowed for any
                       Security Services works or associated works with Security.
                       No Quantity or specification has been provided for Lockers -We have made no allowance for
                       any new lockers or associated items.
                       No Remediation Methodology for Brickwork has been provided-  We have made no
                       allowance for the repair to existing brickwork inc holes, cracks and makegood areas subject
                       to remediation methodology and service relocation.
                       A developed asbestos removal methodology that encompasses all asbestos present on site
                       (both identified in report and site visit) will need to be developed in conjunction with
                       stakeholders for asbestos removal.
                       No developed platform or access system has been provided – A Design will need to be
                       developed to ensure budget and time constraints are accommodated.
                       Structural engineer is to provide a design solution for alterations to the first-floor truss roofing
                       members (cassette unit installation)
                       Structural engineer is to provide a design solution for the auditorium stage extension.
                       Structural engineer is to provide design methodology for science lab ground floor slab
                       reinstatement.
                       Structural engineer to design penetrations for works associated with the installation of
                       JANDS, Dynaflow, Easy Living Platforms and Dumbwaiters items.
                       Structural engineer is to provide design solution for block work door way to allow access to
                       rear of blockwork.
                       Hydraulic engineer to provide drainage design for rear of blockwork potentially including
                       sump and pump.
                       Irrigation design for façade planting TBC.
                       We have made no allowance as no electrical design has been provided for any works
                       associated with the nominated specified items such as JANDS, Dynaflow, Easy Living
                       Platforms and Dumbwaiters.
                       We have allowed a provisional sum for builders works associated with the nominated
                       specified items such as JANDS, Dynaflow, Easy Living Platforms and Dumbwaiters.
                       No fire report has been developed and as such the status of the existing system can not be
                       qualified against the electrical engineer’s fire design.
                       No Specific parameters for fire rating of existing steel work have been provided, boss has
                       allowed a provisional sum for this component of works
                       We have made no allowance to replace timber flooring within the seating area of the
                       auditorium
                       We have made no allowance for time involved in structural hold points while designs are
                       being finalised eg, areas such as sub floor ground beam, stage support, stage extension
                       design, hydraulic inspections, regulatory inspections by certifier.






















                                                                                                   9 | P a g e