Summary Scope of Work
            April Sound
            Page 2 of 2

            DRIVEWAYS

            Cement to Asphalt Transition

                       1.  Saw cut driveways totaling 170 linear feet at the following locations: 4123-4131 E Calavar
                          Rd, 4134 Boca Raton, 4206-4210 W Calavar.

            RETENTION BASINS

            Inlet Concrete Channels

                       1.  Remove and export river rock and sediment from the street where valley gutter terminates
                          south towards inlet pipe to basin at Calavar St, NW Return Basin, and Boca Raton Return
                          Basin.
                       2.  Provide and install 160 total linear feet of concrete channel for water drainage into inlet
                          pipe/existing retention basin at above three locations.
                       3.  Remove existing gravel and replace river rock as needed.
                       4.  Cut the basin bottoms and export soils.

            N.W.Channel

                       1.  Widen Channel Inlet and raise existing sewer ring flush with new concrete channel.

            SOILS

            Subgrade Stabilization

                       1.  Cement stabilize existing subgrade (below asphalt) totaling 15,820 sq ft:
                              a.  Phase One totaling 4,000 sq ft.
                              b.  Phase Two totaling 8,154 sq ft.
                              c.  Phase Three totaling 3,666 sq ft.

            MISCELLANEOUS ITEMS

                                                                   st
                       1.  Install safety handrail at Boca Raton & 41  Lane