S.  Documents to be required      Approving
 No.  Actions  Timelines            Authority             Remarks

 (b)  Whether  IA  has  sampled
 the Indian exporters, if yes,
 proceed to (iv) below. If not,
 request EOI to request IA for
 the sampling of the Indian
 exporters.

 (c)  Whether  HS  Code,  POI  ,
 AUL   for the Capital Asset
 and Injury Period  provided,
 if yes, proceed to (iv) below.
 If not, request EOI to take-
 up the matter with IA.
 (iv)  Concerned EPC is requested to  • TDW:  3-days  from  the   SO (TDW)
 provide the followings:   receipt of the complete
 questionnaire  and
 (a)  IEC & PAN of the mandatory
 respondents and its cross-  details of the Mandatory
 owned companies,   respondents.
 • EPC:  2-days  from  the
 (b)  HS Code of the product, in
 Indian Harmonized system,  receipt of request form
 TDW.
 (c)  SION of the product,
 • Mandatory Respondents:
 (d)  Details of the benets   5-days from the receipt
 availed by the mandatory   of  a  request  from  the
 respondents on the   TDW.
 Schemes mentioned in the
 Questionnaire.
 (e)  Contact person in the
 company for future
 communication.