Page 225 - MJC submissions
P. 225

16. The architect’s admission that the proposed scheme was “very different” from the pre-
                   application design destroys the claim that there was no requirement to consult AWVC.

               1.4   The Third Reference: Application Forms
               17. The third reference appears on the Application Forms. The first form, dated 13  April
                                                                                              th
                   2018 (Folio 1), states that no pre-application consultation had taken place and the
                   replacement form, dated six days later on 19  April 2018 (Folio 32) states that it had and:
                                                              th
               “Feedback stated that the proposed layout was unsatisfactory and gave the following advice.
               A minimum of 50 dwellings would be expected.  30% affordable housing requirement.  High
               density supported (3+1 storeys)------ recommend contemporary design….. etc”.
               The form stated that the meeting had taken place in October 2016 with Mr King.  He
               processed the application and did not deny being involved in the consultation. His tune
               changed later on (see paragraph 2.21).

               18. Both forms were certified as true and correct and submitted by Darren Page, of Lytle
                   Associates. The revised version states that there had been proposals for 70 and 68 units
                   whereas the Design and Access Statement says the pre-application had been for 90.

               1.5   The Fourth
               1.6   Reference: File Note of 20  August 2018 Meeting
                                            th
               19. The fourth reference to the consultation was in the file note prepared by Lytle Associates
                   of a meeting on 20  August 2018 (see the summary at Attachment 5 and folios 100-103)
                                     th
                   to explain why a detailed schematic of the WH:LIC development had mysteriously
                   appeared at page 34 of the Design and Access Statement (Attachment 12).




               It says:

               The “sketch plan” was “only to illustrate that the application scheme does not inhibit the
               neighbouring site coming forward in the future. The approach was suggested in the previous
               pre-application response”. This is not strictly true.
               Mr King appears to have accepted this explanation, without question, but it is not credible,
               and it is much more likely that the integrated plan was included by accident:

                    •  It is the only mention in over 2,000 pages of application data of any intention to
                       develop the WH:LIC site;

                    •  It is not a “sketch plan” but a detailed drawing. The numbering of plans in the Design
                       and Access Statement suggests that large blocks of drawings had been redacted:
                       probably because they related to the WH:LIC site;

                    •  The plan of WH:LIC site enclosed with the original application (Attachment 7) –
                       which was the only clue of the integrated development - was removed from the
                       revision;

                    •  There was no requirement in the pre-application meeting to produce drawings: the           Page 19
                       advice was to ensure that “consideration should be given to the “adjacent allocated
               E:\Cobasco\Personal,  House and computer instructions\EDF and WH Development\MJC
               Plans theories and Objectives\CONSOLIDATED SUBMISSIONS\4a Mr Ashcroft 7th Dec
               2018.docx
   220   221   222   223   224   225   226   227   228   229   230