Page 18 - Safety
P. 18
2020 -21
1. Yard accidents and Other incidents: 02
Sl Cause, Casualties,
No Brief description Cost of damages & Status/Penalty
of accident Committee Responsibility imposed
1 22.07.2020 Cause: Primary: “Removal from
Three BRI staff Casualties: Sri Binay kumar service with
working on the 1 Bridge staff samal,SSE/Bridg immediate effect”
bridge b/w CTF- (Engineering) es/SC and his service is
VKB on up line Cost of damages: terminates with
at km no 114/32 Committee: effect from
were Run over Sr.DSO/SC, Sr 24.11.2020
and killed by DEN/W/SC, Sr Secondary:
DSL/MU DOM/SC Sri N.Pratap Died in the
(70366+12591) Reddy,Errector II incident
On 16.11.2020 Cause: The Primary: WDSG
2 at about 20.15 derailment is due siding
hrs while BOXN to residual material authorities/WD ACC/WD/C Rly
empty rake Gypsum of 5 tones i.e. M/S
rolling into R &D on LH side of the ACC/WD for
line, One BOXN wagon is the cause failing to
empty wagon for the derailment unload the
derailed after with contribution entire
passing R&D from versine consignment of
line point. variations at two Gypsum
Formation while location before material during
rolling into R&D point of mount. unloading.
line, the said Casualties: Nil
wagon RH side Committee: Secondary: nil
wheel off Sr DME/Co-ord, Sr Blameworthy: Withholding of 02
loaded while DSO, Sr DCM & Sr In-charge sets of passes
negotiating DEN/W PWI/NPL
R&D line curve
2021 -22(As on 31.10.21)
1. Train accidents – Nil
2. Other/Yard accidents-Nil