Page 47 - ENGINEERING
P. 47

5. LONG DURATION SPEED RESTRICTIONS CONTINUING FOR MORE THAN
                7 DAYS AS ON 19.11.2021

                                            Kilometre                       Time Loss (min)  Nature of work
           S.  Sr.DEN/     OL   Block   UP/  From  To                                        (Total/Cumulativ Classifi
           N           or          DN                     SR     Date     Plan   Un-   Cons
           o    DEN   CN   Section  /SL                                   ned planned    tn     e/Weekly    cation
                                       Km   TP  Km   TP                                         Progress)
                                                         WD -SC (DN)

                                                                                            Gate road work
           1  WD-SC   OL TDU-Yard  DN   70  8   70   10   50   11-Nov-21  1.00                                P
                                                                                            on progress
           2  WD-SC   OL TDU-Yard  DN   71  16  71   18   75    1-Nov-21  0.33              COT               P

           3  WD-SC   OL TDU-RMY   DN   74  4   74    6   60   26-Sep-21  0.33              COT               P
           4  WD-SC   OL SNF-Yard  DN 175   36  176   6   50    9-Nov-21         1.00       Rough running     O
                                                                                            Painting work at
           5  WD-SC   OL HSJ-SC    DN 192   32  193   6   30    2-Nov-21         2.13                         O
                                                                                            Br.no: 244, 245
                                                      Total               1.67   3.13   0.00

                                                 TOTAL TIME LOSS                 4.80

                                              ENGG.TIME ALLOWANCE               21.00


                                                         SC-WD (UP)
                                                                                            CMS-X-Ing
           1  SC-WD   OL SNF-Yard  UP  174  27  174  25   30    4-Nov-21          2                           B
                                                                                            renewal Pt No:11A
                                                      Total               0.00   2.00   0.00
                                                 TOTAL TIME LOSS                 2.00

                                              ENGG.TIME ALLOWANCE               21.00
           A) Due to Condition of T/out Sleepers           F)  Due to Corroded /Wornout Rails/Bent rails

           B) Due to Condition of Switches/Xings          G) Due to Rail/Weld Failure
           C) Dute to condition of Br Timbers             H) Due to Formation Problem

           D) Due to Ballast Defficiency                  P)  Sanctioned Works like CTR/DS/TWR/Br
           E) Due to scabbed Rails                        O) Others
   42   43   44   45   46   47   48   49   50   51   52