8.1 USFD PROGRAMME/PROGRESS OF SC DIVISION AS ON
OCTOBER 2021 (UP TO 25-10-2021):
Cumulative Progress
Annual
Testing Description upto 25-10-2021
Target in KM
in KM
RAIL TESTING NBC/GFC/NGFC 7459 5129
D' MARKED RAILS 150 88
SERVICE WELDS 1165 450
HIGH EMBANKMENT & CUTTINGS 114 69
CURVES 155 88
NEW WELDS 300 135
DFWO 37 23
TEST FREE RAILS 96 96
RAILS WINTER PRECAUTION 155 155
LOOP LINES 241 117
FRACTURE PRONE(FBW) 0 0
FRACTURE PRONE(SKV) 30 5
SWITCHES 374 369
SCABBED RAIL TESTING 0 0
SEJ's TESTING 0 0
BRIDGES AND ITS APPROACHES 324 324
TOTAL PROGRESS 10600 7048
1.USFD testing over due - NIL
2. Workload is for 31 operators but the available operators are only 15, against
sanction of 28.