Page 51 - ENGINEERING
P. 51

8.1 USFD PROGRAMME/PROGRESS OF SC DIVISION AS ON
                  OCTOBER 2021 (UP TO 25-10-2021):


                                                                                  Cumulative Progress
                                                                 Annual
            Testing Description                                                     upto   25-10-2021
                                                              Target in KM
                                                                                          in KM

            RAIL TESTING NBC/GFC/NGFC                             7459                     5129

            D' MARKED RAILS                                        150                      88


            SERVICE WELDS                                         1165                     450

            HIGH EMBANKMENT & CUTTINGS                             114                      69


            CURVES                                                 155                      88


            NEW WELDS                                              300                     135

            DFWO                                                    37                      23


            TEST FREE RAILS                                         96                      96


            RAILS WINTER PRECAUTION                                155                     155

            LOOP LINES                                             241                     117


            FRACTURE PRONE(FBW)                                      0                       0


            FRACTURE PRONE(SKV)                                     30                       5

            SWITCHES                                               374                     369


            SCABBED RAIL TESTING                                     0                       0

            SEJ's TESTING                                            0                       0


            BRIDGES AND ITS APPROACHES                             324                     324


            TOTAL PROGRESS                                        10600                   7048


            1.USFD testing over due  - NIL


            2. Workload is for 31 operators but  the available operators  are only 15, against
            sanction of 28.