Page 8 - Mech (C&W) info
P. 8

No. of Rakes       No. of wagons        Wagons attended
                                Year                loaded        attended in sidings        per Month

                          2019-20 (Apr-Mar)           8,258               35,798                 2,983


                          2020-21 (Apr-Mar)           8,109               37,168                 3,097

                          2021-22 (Apr-Oct)           7,187               27,464                 3,923

                     This has resulted in increased availability of wagons for traffic use thus
                     increased revenue.


               iii.  Retrofitment  of  Twin  pipe  air  brake  system  on  wagons:  At  RDM
                     freight  Depot,  retrofitment  of  twin  pipe  air  brake  system  has  been
                     done on 1375 wagons and at SNF, retrofitment has been started in
                     Sep-21 and 40 wagons have been completed till now.


               iv.  Conversion  of  20.3T  axle  load  BLCA/BLCB  wagon  to  22T  axle  load
                     BLCAM/BLCBM wagon: To increase the carrying capacity from
                                                                                          , conversion of
                     existing 20.3T axle load BLC rakes to 22T axle load BLCM rakes is

                     being done at SNF depot. Material is supplied by M/s CONCOR
                     for 315 wagons and up gradation is done departmentally at SNF
                     during ROH attention on 300 BLC wagons till now.

               v.    Tyre turning of wheel sets for BLC/BOXN wagons at Pit Wheel lathe of
                     SC  depot:  Tyre  turning  of  829  defective  wheel  sets  of  BLC/BOXN

                     wagons was carried out at Pit wheel lathe of SC coaching depot
                     during  the  year  2021-22(Apr  Oct).  Earlier  defective  wheels  were
                     being  sent  from  SNF  to  RDM  for  tyre  turning.  This  system
                     improvement  has  avoided  the  movement  of  lorry  from  SNF  to
                     RDM  and  back  for  tyre  turning  of  wheel  sets  thereby  saving  lot  of
                     time and money.


               vi.                                                 : 840 wagons were attended by
                     giving  intense  repairs  at  RDM  &  BPA  freight  depots  during  the
                     current year 2021-22(Apr Oct).

               vii.  Quick  Watering  System  at  SC  station:  Quick  coach  watering

                     system  has  been  fully  automated  at  Secunderabad  Station  to
                     reduce  the  time  taken  for  filling  the  water  in  the  coaches.  To
                     achieve this existing pumping system has been replaced with a
                     New  Automatic  Coach  watering  system  having  6  nos.  of  20  HP
                     pumps.













                                                                                                        8