Page 10 - Electrical (M)
P. 10

2x120 kVA Modular UPS at PRS/SC
            2.4    Air conditioning of Running Room(Make shift) at TDU:
                  Due  to  shortage  of  beds  for  crew  resting  at  TDU,
                   Quarter No.1/1 is being utilized as Running room. Air-
                   conditioning, lighting & power supply arrangements
                   works  were done in order  to improve  the quality of
                   rest to crew halting at this running room.





            2.5    Reduction of CMD for Existing HT Connection at HYB:
                  CMD has been reduced from 750 kVA to 520 kVA atHT Service connection HDC-
                   001  feeding  the  Hyderabad  station,  IOH  shed  &  staff  quarters  to  avoid  excess

                   fixed  charges.  Savings  of  about  Rs.  10.9  lakh/Annum  can  be  achieved  by
                   reducing CMD.

                        Sl No  Location       Service No          Existing CMD           Revised CMD
                        1       HYB           HDC-001 Cat-III  750                       520


            2.6    Safety Week from 3  to 10  May
                                             rd
                                                      th
                  Safety week was observed in the first week of May to reiterate the importance of
                   safety while working. Safety Seminars have been conducted all over the division

                   at  various  depots  &  sub-depots  to  create  awareness  about  safety.  Staff  have
                   been  educated  and  demonstrated  to  follow  Electrical  safety  precautions  while
                   working on OH lines &other electrical equipment.