S. Target During Cumulative
No Description of items 2020-21 2021-22 Oct.-21 2021-22
AC coaches 211 438 39 270
TL coaches 41 243 0 19
3 V-Belts failures – No. of incidences
AC coaches – (No. of sets) 10 122 3 12
TL coaches - (No. of sets) 25 222 0 12
Scheme of bypass provision
of extending supply to
4 OMS/RA coach from power 5 32 3 26
car as per RDSO letter dated:
09/04/2019
Provision of Test benches
HOG test-kit for testing IV/UIC 1 1 0 1
5 coupler continuity test
MMR calibration test 1 2 0 0
Micro Controller simulation kit 0 2 0 0
Software developments
Monitoring of muster including
OT/TA, Sick & Leave etc., of Comple Complet
all maintenance & escorting ted ed 0 0
6 staff through google spread
sheet
Monitoring of fuel Comple
consumption & energy ted EOG/HYB 0 0
consumption in power cars (1)
through google form EOG/SC
Provision of additional
switches to control luggage
7 room lights from 6 45 17 34
VFH/charging box provided in
gards
Test bench for calibration of
safety devices of DG sets
8 (lube oil pressure, water -- 2 0 0
temperature relay/sensor,
RPM, etc.,)
Downloading of
Microprocessor data for
9 100% 10% 3% 6%
analysis & AC unit
performance
Innovations/system
10 5 3 0 1
improvements