        RMX goes hybrid                                                                                          Ready-mix




        Opportunity             Results                                                                      QATAR
        Enhancing energy        •  30–40% diesel fuel
        efficiency of a diesel-  savings
        powered RMX facility    •  Fewer diesel generators
        by addressing power      required on site
        demand fluctuations.     (downsizing)
                                •  Generator runtime
        Solution                 reduced by 15% in
        Installing an energy storage   summer, over 50% in
        system solution (battery   winter
        storage capacity: 307 kWh)   •  System stability
        that is synchronized with   improves efficiency and                                              Jon Brooks
        the diesel generator and   reliability                                                         General Manager
        provides the power needs   •  CO₂ emissions
        in the most efficient way.  reduction: 180 tons/year
        Complement the solution   •  ROI: 3 years
        with a solar array on the
        roof which generates
        20 kW and can be
        expanded further in future.
        Cost: 110 kCHF
        Timeline: 5 months
                                                                                                        Sadique Anwar
                                                                                                         Head of HSE