               15.3 CABLE DEFECTS / CUTS / THEFTS BY MISCREANTS:

                       Use of cable route locators for survey is made compulsory. Integrated cable
                      path diagram was made. Criminal cases are registered against the agencies
                      that are cutting cables in addition to imposing penalties.
                      Defective  cables  identified  by  carrying  out  Cable  meggering  at  regular
                      intervals (89 locations done in 2022-23 till date) and replaced about 43.26 Km
                      of defective cable in 2022-23.
                      ELD’s are provided at all stations and monitored through Data logger.

               16. POWER SUPPLY ARRANGEMENTS:

                      At  144  stations  integrated  power  supply  system  out  of  145  stations  and  one
                      stations not required, since temporarily closed and at IB /LC/stations 122 no. of
                      Mini  Integrate  Power  supply  system  is  provided.  The  other  stations  have
                      discrete systems consisting of battery chargers and secondary cells for each
                      application. The following works are planned for improvement in power supply
                      scenario.

                          Non Blanking of Stations/LC gates/Auto sections:
                        ●  The work of strengthening of power supply arrangement in Auto signaling
                           section between SNF-LPI sanctioned in LSWP 2017-18. LPI – HFZ –SNF –HSJ
                           Auto section Mini IPS provided and achieved Non- blanking signals. HSJ-
                           HYB Auto section Mini IPS provision work is under progress (TDC: 12/2022).

               17.  ASSET FAILURES – ACTION PLAN TO MINIMIZE

                  I   Point failure
                                                                                                     Not
                 A  Replacement of GRS 5E point machine with IRS point machine.
                                                                                                 applicable

                 B  Replacement of wooden layout by PSC layout                                         0

                 C  Replacement of point contactor relays                                             Nil

                 D  Point failure due to miscreant activities.                                        03
                     Compliance for joint inspections of points & crossings
                 E  i) Clearance of ballast to be done                                                NIL
                     ii) Providing of ‘J’ clips to be done
                  II  Track circuit failures
                      Track circuit failures due to improper drainage & inadequate
                 A                                                                                   15
                      ballast
                  B  Replacement of block joints with glued joints.                                   0

                 C  Track circuit failures due to miscreant/OSI activities.                          04