2.    Achievements (Highlights):



               i.    Commissioning  of  Extension  of  ROH  shed  at  SNF  freight  depot:
                     Extension  of  ROH  shed  at  Sanath  nagar  depot  was
                     commissioned.



















                     Earlier  ROH  shed  was  of  55m  length,  which  is  not  sufficient  to
                     carry  out  the  ROH  attention  of  one  BLC  unit  consisting  of  5

                     wagons  (length  of  one  unit  is  around  70m).  To  overcome  this
                     problem, ROH shed has been extended for another 50m so that

                     ROH  attention  and  Sick  attention  requiring  lifting  can  also  be
                     undertaken in covered shed.
               ii.  Commissioning of CNC Surface Wheel Lathe at SNF freight depot:

                     CNC  surface  wheel  lathe  at  Sanath  nagar  depot  was
                     commissioned.



















                     Earlier,  the  defective  wheels  were  sent  to  RDM  depot  &  SC  for
                     tyre  turning  of  wheels  &  UST  which  was  time  consuming  and

                     resulting  more  time  in  releasing  of  sick  wagons.  Availability  of
                     wheels  at  SNF  freight  depot  has  improved  after  installation  of

                     surface wheel lathe.

               iii.  Commissioning of Automatic Coach Washing Plant (ACWP) at SC
                     &  HYB  depots:  Automatic  Coach  Washing  Plants  (ACWP)  were
                     commissioned  at  SC  &  HYB  Coaching  depots.  The  automatic

                     coach  washing  plant  is  able  to  achieve  complete  exterior
                                                           137