waiting hall with 40 Sq m are available.  As
                                                                                                          per  the  need/necessity  and  Railway  bard
                                                                                                          norms,  the  facilities  like  provision  of
                                                                                                          platforms and other amenities at KZJ town
                                                                                                          will   be    studied    and    proposed     by
                                                                                                          Commercial department.
               12    Shri. B. Venkatesh     Peddapal       NIL      8.RUB  at  LC  No.  32  at  Tharaka  8.Remarks:
                     Netha Hon’ble MP   li                          Rama  Nagar  Village  in  KOLR  –  Road Over Bridge was sanctioned in 2017-
                     ( Lok Sabha )          Parliame                PTKP Section.                         18 on Cost sharing basis at a cost of Rs.72.17
                                            ntary                                                         Cr. (Railway share: Rs 28.17 Cr, State share:
                                            Constitu                                                      Rs  44.00Cr).  General  arrangement  drawing
                                            ency                                                          approved by both Railway and State Govt.
                                                                                                          Approach  estimate  is  awaited  from  State
                                                                                                          Govt  for  framing  of  combined  estimate  &
                                                                                                          sanction  to  undertake  the  work.  Reminder
                                                                                                          sent on 12.05.22

                                                                                                          9.Remarks:
      395
                                                                    9.RUB     at   LC    No.    33    at   Box  pushing  completed.  Approach  work
                                                                    Haripuram  Village  in  KOLR  –  and  misc  works  are  in  progress.  Presently
                                                                    PTKP Section.                         progress  is  stalled  by  Rains.  Work  will  be
                                                                                                          recommenced  soon  after  cessation  of  rains
                                                                                                          and Work is anticipated to be completed by
                                                                                                          Feb '23

                                                                                                          10.Remarks:
                                                                    10.  RUB  at  LC  No.  35  at  Box  casting  is  completed.  Approach  work
                                                                    Kothapally  Village  in  PDPL  - and  misc  works  are  in  progress.  Presently
                                                                    KOLR Section.                         progress  is  stalled  by  Rains.  Box  pushing
                                                                                                          work will be started soon after cessation of
                                                                                                          rains  and  Work  is  anticipated  to  be
                                                                                                          completed by Feb '23.

                                                                                                          11 Remark:
                                                                    11.  RUB  at  LC  No.  38  at  RUBs                sanctioned        in       Works