Page 400 - GM E-BOOKLET 2022
P. 400
Divisional
Engineer/North/Secunderabad(Phone No.
9701371203) for a joint inspection to decide
the alignment, drainage arrangements,
connecting roads, etc.
23. Non closure of LC No. 56 23. Remarks
near Rechini Road Railway Indian Railways is in the process of
Station, Tandur village and eliminating all LCs in view of safety of
Mandal, Mancherial District passengers as well as public. The requested
location is LC No.66 at km.229/28-30
between Rechini Road-Repallewada
stations on Kazipet-Ballarsha section. Road
Under Bridge has been sanctioned in lieu of
this LC. District Collector, Mancherial has
given consent for Closure of LC No. 66 by
RUB. RUB work is in progress. This gate
will be closed only after completion of Road
398
under bridge work. Work is anticipated to
be completed by FEB/23.
24. RUB at LC No. 37 Km 299/2-6 24. Remarks
between KOLNUR- PEDDAPALLI Box casting and approach works are in
Jn progress. Work is anticipated to be
completed by March '23
25. RUB at LC No. 66 Km 229/27-29 25. Remarks
between RECHNI ROAD –
REPALLEWADA Box casting completed. Misc works are is in
progress. Work is anticipated to be
26. RUB at LC No. 68 Km 226/11-13 completed by FEB/23.
between RECHNI ROAD –
REPALLEWADA. 26. Remarks
RUB work is Sanctioned in July’22 . RUB
work is proposed for deletion due to
drainage not feasible.