Page 400 - GM E-BOOKLET 2022
P. 400

Divisional
                                                                                                          Engineer/North/Secunderabad(Phone  No.
                                                                                                          9701371203) for a joint inspection to decide
                                                                                                          the  alignment,  drainage  arrangements,
                                                                                                          connecting roads, etc.

                                                                    23.  Non  closure  of  LC  No.  56  23. Remarks
                                                                    near  Rechini  Road  Railway  Indian  Railways  is  in  the  process  of
                                                                    Station,  Tandur  village  and  eliminating  all  LCs  in  view  of  safety  of
                                                                    Mandal, Mancherial District           passengers as well as public. The requested
                                                                                                          location  is  LC  No.66  at  km.229/28-30
                                                                                                          between       Rechini      Road-Repallewada
                                                                                                          stations on Kazipet-Ballarsha section. Road
                                                                                                          Under Bridge has been sanctioned in lieu of
                                                                                                          this  LC.  District  Collector,  Mancherial  has
                                                                                                          given consent for Closure of LC No. 66 by
                                                                                                          RUB.  RUB  work  is  in  progress.  This  gate
                                                                                                          will be closed only after completion of Road
      398
                                                                                                          under bridge  work. Work is anticipated to
                                                                                                          be completed  by FEB/23.

                                                                    24.  RUB  at  LC  No.  37  Km  299/2-6  24. Remarks
                                                                    between  KOLNUR-  PEDDAPALLI  Box  casting  and  approach  works  are  in
                                                                    Jn                                    progress.  Work  is  anticipated  to  be
                                                                                                          completed by March '23

                                                                    25. RUB at LC No. 66 Km 229/27-29     25. Remarks
                                                                    between    RECHNI  ROAD  –
                                                                    REPALLEWADA                           Box casting completed. Misc works are is in
                                                                                                          progress.  Work  is  anticipated  to  be
                                                                    26. RUB at LC No. 68 Km 226/11-13     completed  by FEB/23.
                                                                    between    RECHNI  ROAD  –
                                                                    REPALLEWADA.                          26. Remarks
                                                                                                          RUB  work  is  Sanctioned  in  July’22  .  RUB
                                                                                                          work  is  proposed  for  deletion  due  to
                                                                                                          drainage not feasible.