Page 399 - GM E-BOOKLET 2022
P. 399
18. Widening of RUB at Bridge 18. Remarks
No. 90 at Km 15/6.1 in PDPL – This is a waterway bridge and not meant
KRMR Section. for passage of traffic. Either side no
approach roads (only fields).
19. Widening of RUB at Bridge 19. Remarks
No. 164 at Km 23/0, 24/0 in Additional vent way feasible and work can
PDPL-KRMR Section. be considered on full deposit terms, if state
Government comes forward.
20. Widening of RUB at Bridge 20. Remarks
No. 188 at Km 30/5.6 in PDPL – Additional vent way feasible and work can
KRMR section. be considered on full deposit terms, if state
Government comes forward.
21. Mancherial Assembly 21. Remarks
Constituency – requesting for The line mentioned in the subject belongs to
397
providing Railway gate with M/s. SCCL. M/s. SCCL has been requested
appointment of Guard on newly to eliminate this LC by providing RUB or to
constructed single line track man the gate. Action is to be initiated by
across road from Krishna Colony M/s. SCCL.
to CCC Road. (MLA letter
16.09.2019).
22. RUB on full deposit terms at 22. Remarks
Railway Culvert No. 150, Rajiv Railway Bridge No. 150 is a waterway
Nagar, Mancherial Town and bridge between Mancerial and Mandamari
District. stations. It is feasible to construct a Limited
Height Subway of 2.50m height at about
100m away from the existing Railway
Bridge No.150 on full deposit terms. The
approximate cost would be Rs 5.40 Cr. In
this regard, it is requested to advise
concerned Road authorities to approach Sr