Construction of RUB @ L.C 51



               1.3.4. RAILWAY AFFECTING TANKS (RATs):
                  Joint inspections have been carried out by ADENs with State Government
                    authorities.
                  Considering the condition of the tanks, if any repairs are to be carried out,
                    the  same  are  noted  and  State  Govt.  authorities  have  been  advised  to
                    carry out the repairs within a targeted date

               1.4. SAFETY

                     Special emphasis has been laid on safety in the division. The following
                     measures are being taken

               1.4.1 SAFETY DRIVES (Upto Oct’ 2022)


                                                                                  No of
                S.No       Safety drive issued by             Frequency                      Remarks
                                                                                  drives

                  1     CTE special drive                 Once in a month           7        Attended

                        Night  surprise  foot  plate
                  2                                       Once in a month           10       Attended
                        inspection

                        Safety  drive  as  per  Rly
                  3                                       15 days drive only        8        Attended
                        Board order

                        Special  drive  on  Bridges
                        includes  FOBs  /  ROBs  as
                  4     per  Railway  Board  letter        Quarterly safety         1       Completed
                        2016/52/CE/III/BR/Safety                 drive
                        Dt: 09.07.18.