Page 257 - GM E-Booklet Dec-2022
P. 257
2 145 ROB between Dichpally - 2012-13 Foundation design submitted to
Nizamabad two lane in lieu of LC HQrs on 18.11.2022, under proof
No 193 check.Joint inspection/relocation of
S&T and Telecom cable conducted
on 23.11.2022.
To take up the foundation work S&T
cable to be shifted.
TDC - Oct 2023.
3 220 ROB between Gundla 2017-18 Combined estimate preparation is
Pochampally - Medchal four lane pending due to non-receipt of
in lieu of LC No 246/A approach estimate from State Govt.
State Govt. has been again
requested on 28.11.2022 to submit
their portion of estimate.
4 192 ROB between Mahboobnagar - 2016-17 State Govt is finalising the
Manyamkonda in lieu of LC No 60 alignment plan and will submit to
Rly shortly, as per their letter dated
17.11.2022.
5 234 ROB between Falaknuma - 2018-19 Tender opened on 28.10.2022 and
Budvel four lane in lieu of LC No 7 under finalisation.
Permission to HMWSSB for shifting
their water supply line in Railway
area is under process.
6 232 ROB between Timmapur - 2018-19 State Government given initial
Shadnagar four lane in lieu of LC approval of GAD on 22.11.2022 and
No 27 submitted to Division for review.
Estimate under preparation.
7 238c Proposed ROB as 1x46.00M clear 2019-20 Alignment plan received from State
span composite steel girder at Km Govt in July 2022. GAD under
166/500-600 in lieu of Existing preparation.
Manned LCNo.90A between
Wanaparthy road and
Sriramnagar stations.
8 238d Sec-bad-Mudkhed- ROB in lieu of 2019-20 Alignment submitted by State
LC 228 Wadiyaram Yard- Government (July 2022).
Masaipet at Km 555/3-4. GAD prepared and submitted to Div
(23.11.2022) for initial comments.
9 238f Sec-bad-Mudkhed- ROB @ LC 2019-20 Joint inspection conducted with
No.250 (Bolarum Yard) - Cavalry HRDCL authorities on 29.11.2022
barrack. for fixing up alignment plan for
preparation of GAD.
10 238g Sec-bad-Mudkhed-ROB @ LC 2019-20 Soil particulars and trial pit details to
No.209 A uppalvai-Kamaredddi be incorporated in GAD. Boring to
collect Soil particulars completed
(22.11.2022) and details are being
incorporated in GAD, under
progress.
11 238h Jankampet-Bodhan- ROB @ LC 2019-20 GAD under revision, as submitted
No. 12JB at km 12/5-6 by construction having some
infringement issue for future
doubling/tripling.
255