Page 195 - GM's Annual Inspection Booklet DEC- 2022
P. 195

Planning

            WORKS SANCTIONED - WORK IN PROGRESS (WIP)
              I.
            A.     New Lines – (Executive Agency: Construction)

            DEVARKADRA-KRISHNA SECTION (65.82 KMs) - TDC-2023
            Maganur-Krishna  (13.17  KMs)  -  The  entire  section  shall  be  commissioned  along  with
            Electrification and Absolute Block System of working with 03 Block stations i.e., Marikal, Jaklair
            and Maganur.

            MANOHARABAD-KOTHAPALLI SECTION (151.36 KMs) - TDC-2025
            Kodakandla-Duddeda (21.50 KMs)
            Duddeda-Sircilla (48.20 KMs) for utilization of Goods sheds at Siddipet & Sircilla.
            Sircilla-Kothapalli (39.01 KMs)


            B.     Doubling: (Executive Agency: RVNL)
                   Section                                                                   KMs
                   STPD „A‟-STPD „B‟ Cabins Chord Lines                                      0.7
                   MJF - MLYG UP By-pass line                                                3.57


            C.     RE Works: (Executive Agency: CORE)

                   Section                                            KMs                    TDC
                   1. SC-MUE section
                     a)  Kamareddi-Nizamabad                          51.84              31.03.2023
                     b)   Janakampet-Mudkhed                          82.02              31.03.2023
                   2. SC-DHNE section
                     a)   Kurnool City-Gadwal                         55.47              31.03.2023



            D.      Traffic Facility Works (PH-1600):
                  Sl.  Description of work                                             Cost        TDC
                  No.                                                                 (Crs)
                   1.  Jukal: Provision of New crossing station at Jukal              16.95     31.03.2023
                        between Umdanagar & Timmapur on SC-MBNR section
                        for exclusive dealing of freight operations & to ease out
                        TMX/PFT.
                        Year of Sanction: 2010-11
                        Executive Agency: RVNL
                   2.  Perur: Provision of new crossing stations (Perur)               8.80     31.03.2023
                        between Wanaparthy-Kaukuntla (18.27 kms)
                        Year of Sanction: 2017-18
                        Executive Agency: Engg. Open Line
                   3.  Jankampet Jn: Additional two loop lines. However,              11.30     30.06.2023
                        work is being executed with additional single line. Year
                        of Sanction: 2021-22
                        Executive Agency: Engg. Open Line