Planning
WORKS SANCTIONED - WORK IN PROGRESS (WIP)
I.
A. New Lines – (Executive Agency: Construction)
DEVARKADRA-KRISHNA SECTION (65.82 KMs) - TDC-2023
Maganur-Krishna (13.17 KMs) - The entire section shall be commissioned along with
Electrification and Absolute Block System of working with 03 Block stations i.e., Marikal, Jaklair
and Maganur.
MANOHARABAD-KOTHAPALLI SECTION (151.36 KMs) - TDC-2025
Kodakandla-Duddeda (21.50 KMs)
Duddeda-Sircilla (48.20 KMs) for utilization of Goods sheds at Siddipet & Sircilla.
Sircilla-Kothapalli (39.01 KMs)
B. Doubling: (Executive Agency: RVNL)
Section KMs
STPD „A‟-STPD „B‟ Cabins Chord Lines 0.7
MJF - MLYG UP By-pass line 3.57
C. RE Works: (Executive Agency: CORE)
Section KMs TDC
1. SC-MUE section
a) Kamareddi-Nizamabad 51.84 31.03.2023
b) Janakampet-Mudkhed 82.02 31.03.2023
2. SC-DHNE section
a) Kurnool City-Gadwal 55.47 31.03.2023
D. Traffic Facility Works (PH-1600):
Sl. Description of work Cost TDC
No. (Crs)
1. Jukal: Provision of New crossing station at Jukal 16.95 31.03.2023
between Umdanagar & Timmapur on SC-MBNR section
for exclusive dealing of freight operations & to ease out
TMX/PFT.
Year of Sanction: 2010-11
Executive Agency: RVNL
2. Perur: Provision of new crossing stations (Perur) 8.80 31.03.2023
between Wanaparthy-Kaukuntla (18.27 kms)
Year of Sanction: 2017-18
Executive Agency: Engg. Open Line
3. Jankampet Jn: Additional two loop lines. However, 11.30 30.06.2023
work is being executed with additional single line. Year
of Sanction: 2021-22
Executive Agency: Engg. Open Line