S.No  Name of the siding                                                        Siding
                  B)     “Green Field Private Freight Terminal” at Uppalwai (UPW) station by    Private
                         M/s Mahalaxmi warehousing, Warangal.
                Status:
                 1. Application submitted on 24.02.2021.
                 2. Project Feasibility Report and Conceptual plan on 24.02.2021.
                 3. Application fees submitted on 03.05.2021.
                 4. In-Principle approval at Divisional level and DRM approval accorded on 01.10.2021.
                 5. In-Principle approval at Zonal level accorded on 03.01.2022.
                 6. Consultant submitted ESP on 20.01.2022 under new GCT policy.
                 7. Final ESP submitted by consultant, approved at Divisional level and approved by CE/P&D
                   on 26.04.2022.
                 8. Intimated to party on 27.04.2022 to submit modified DPR basing on approved ESP.
                   TDC-31.03.2023



                S.No.  Name of the siding                                                          Siding
                  C)     “M/S  TGV  Sri  Rayalaseema  Alkalies  and  Allied  Chemical  Ltd”  at    Private
                         Alampur (ALPR) station by M/s TGV SRAACL, Kurnool.
                Status:
                  1. Consultant  submitted  the  application  on  25.03.2022  under  New  GCT  policy  for  further
                    process.
                  2. Application Fees paid on 29.03.2022
                  3. In Principle Approval issued on 13.04.2022.
                  4. Final ESP approved by CE/P&D on 14.05.2022.
                  5. Intimated to party on 27.04.2022 to submit modified DPR basing on approved ESP.
                  6. FDR  of  Rs.10  Lakhs  towards  Refundable  Security  deposit  had  submitted  by  party  on
                    20.05.2022 and same was deposited to Sr. DFM/HYB.
                  7. Final DPR submitted on 13.07.22.
                  8. GCT approval given on 14.07.22.
                  9. Construction work to be started by party.
                10.  Land Acquisition in progress.

                    TDC-31.01.23