B. Traffic Facility Works (PH-1600):
Sanctioned Revised
Sl. No. Description of work TDC
Cost (Crs) Cost (Crs)
Nizamabad: Remodeling of yard arrangements
for providing additional platforms and one full-
length dead-end spur.
Required funds in PH-1600 for phase-II.
1. 9.39 12.04 --
Proposed under PWP 2023-24, but not
shortlisted by Hqs.
Year of Sanction: 2018-19
Executive Agency: Engg. Open Line
III. WORKS NEEDS TO BE SANCTIONED UNDER MISSION 3000MT
A. Traffic Facility Works (PH-1600):
Sl. Name of the Work Estimated Proposals under
No. Cost (Crs) PWP/LSWP/Umb.
1. Timmapur: An additional loop line for exclusive 2.99 Under Umbrella works 2022-
dealing of CMCT bound freight trains. 23 Pending with HQs.
2. Kacheguda: (PWP-2022-23) Increasing the 120.38
CSRs of Rd no.3 (610 mtrs), Rd no.4 (579 mtrs)
and Rd no.5 (544 mtrs) to accommodate full
length trains and Extension of shunting neck
from existing 526 mtrs to 730 mtrs duly
constructing bridge on Moosi River.
3. New Crossing Station: Proposal for new
crossing station (Fakhrabad Halt) between 29.86
NVT-BSX at KM 438.52 with One Main Line and
Two Loop Lines.
4. Dupadu: Yard Remodelling along with Goods 23.99 PWP-2023-24
Shed. Pending with RB.
5. Navipet: Provision of additional loop line. 8.91
6. Bolsa: Provision of additional loop line. 8.36
7. Falaknuma: Making Road No‟s 5&6 as full- 8.56
length dead-end spurs.
8. arkadra: Conversion of existing loop line no.2 into
Dev 10.15
Longer Loop line.
9. Divitipalli: Conversion of existing Down loop 11.40
line into Longer Loop line.
10. Bolsa: Conversion of existing loop line into 12.80
Longer Loop line.
11. Masaipet: Conversion of existing loop line into 10.70 PWP-2023-24
Longer Loop line. Pending with HQs.
12. New Crossing Station: Proposal for new
crossing station (Shelgoan Halt) between 44.36
UMRI-SVN at KM 383.53 with One Main Line
and Two Loop Lines.